> Viewing Budget Totals

View budget totals to display the total budgeted dollars by unique cost area, cost center, code of accounts, and budget code class.

Follow these steps to view budget totals.

   The value displayed for Total budget indicates the sum of all budgeted dollars on the Budgets tab grouped by class, cost area, cost center, or code of accounts.

    However, if the PROJTRAK installation parameter is set to OFF, Datastream 7i displays the sum of all budgeted dollars on the Budget tab based only on the class.

  1. View budget totals as necessary, and then click . Datastream 7i closes the Total budget dialog box and returns to the Budgets page of the Projects form.